• Client: MPC
  • Value: $29M
  • Completion date: May 2025

Overview

The Gundaroo Drive Package B Project was a major arterial road upgrade of 3.2km of the existing William Slim Drive between Baldwin Drive and Chuculba Cres. This technically challenging project involved the construction of a new super T bridge over Ginninderra Creek and included the demolition of the existing bridge. Works also included the upgrade of the Owen Dixon Drive Intersection to a signalised intersection.

The project scope also included:

  • Significant pavement works under heavy traffic volumes
  • 19,000t Asphalt Placement
  • 25,000m3 of Bulk Earthworks
  • Box culvert underpasses with RE wall installation
  • 1,300m of Stormwater pipes
  • Existing Manhole Extensions

The project was completed under difficult circumstances including extensive wet weather, cost escalations, supply issues relating to the Ukraine War, and extensive asbestos onsite.